GlobalFoundries Chip-Fab Plant
When GlobalFoundries broke ground on its vast
semiconductor manufacturing facility in Malta last
July, members of Laborers local unions 157 and 190
went to work at the forefront of this huge project.
Construction costs for the first phase of this $4.2 billion
project are estimated at $500 million, with budgets for
subsequent phases still under development as plans and
contracts are finalized.
Current plans call for three 300,000 square-foot manufacturing
modules, with 72 percent of the Luther Forest
site remaining as forest land.
More than 60members began work last year, with smaller
numbers on site this spring and a substantial increase
expected as soon as site work concludes and construction
of the second of three buildings begins.
During the current economic downturn, we feel fortunate
to have a project of this magnitude in the region, and it
looks to be a bright spot in our area for some time to
come,” said Local 157 Business Manager Peter Stearns.
It is also a pleasure to work on a project with a Project
Labor Agreement (PLA), with all trades working together
to complete the project on time and budget.”
Our laborers have been very busy onsite driving foundation
piles, installing lagging walls, excavating, pouring concrete,
stripping and cleaning forms, installing fencing and bollards
and performing general clean up,” explained Anthony
Fresina, Local Union 190 business manager.
The GlobalFoundries semiconductor manufacturing plant
will employ 1,400 workers when it becomes operational
in summer 2012, with an estimated payroll totaling $88
million annually. An additional 5,000 indirect jobs are
projected to be created by construction of the plant and
by the start up and expansion of additional related businesses
serving the plant and its employees. The projected
overall total for this project and the ancillary work
expected to follow is $20 billion over 25 years.
All this activity is focused through a tight deadline that
challenges the Laborers and other trades every day.
From the initial concrete pour in September of 2009,
the contractor has 24 months to turn the facility over to
the owner. Tomeet this deadline, thousands of yards of
concrete needed to be poured daily; and this required
that a concrete batch plant be constructed on site.
To help meet this formidable challenge, the obtaining of
a Project Labor Agreement — a challenge in itself, on a
privately funded project of this magnitude — provides an
important framework. The local building trades councils,
the local trade unions, and the owner reached an agreement
through five months of constant negotiations. State government
was also a key player, recognizing the benefits
of a PLA on the project and granting significant tax
benefits and training grants.
It’s difficult to imagine amore substantial win-win situation
for all involved than this ambitious and very large project,”
said Sam Fresina, Business Manager of the Laborers
Eastern District Council. “It’s a substantial challenge to
our members and contractors; but the benefits are also
substantial.We are proud to be involved and confident
that we can meet this challenge.We always do.”
|